Return to Previous Document The Readjustment of the NSRS FAQ NGS Home Page NOAA Home Page



Home
FAQ
Related Links

 FREQUENTLY ASKED QUESTIONS

When will the new adjustment be finished?
The master plan has initiation of the first layer of the adjustment in June 2005, and completion of the airport layer in October 2006. The regional layers will be adjusted from November 2006 through September 2007.

Could it be completed sooner?
The upper layers proceed sequentially and require set amounts of analysis. The regional layers could be processed simultaneously. It is conceivable that if additional personnel were available, the regional layers could be completed no sooner than April 2007.

When will I see new coordinates in my area?
One will immediately see some new coordinates when National Layer 1 is completed in December 2005. The NGS Integrated Data Base will be updated as each layer is completed. In the event of software development delays, statewide contingency adjustments (without accuracies) will be initiated to insure updated coordinates are delivered as soon as possible to our users.

When will I know if the contingency adjustment is executed for my area?
The National Readjustment Web Page will contain a link showing if the contingency adjustments have begun, and the current contingency schedule.

When will I see these new network and local accuracies?
One will begin to see these fields populated in our data sheets at the same time the new coordinates also appear -- for example, National Layer 1 will be completed in December 2005, and the last region will be completed in September 2007. However, if contingency adjustments are performed, these will not provide the new accuracy values.

What is the deadline for submission of a GPS UDN project for the readjustment?
The National Readjustment Web Page will contain a link showing the current schedule for the regional layers, which will be initiated November 2006 through August 2007. In general, UDN projects must be submitted at least 6 weeks prior to the start of a given region to allow for review and possible reprocessing.

What about classical horizontal control surveys?
The Readjustment of the NSRS will contain only GPS projects. At the completion of the project, datum transformation grids will be developed to support those legacy data.

Will the currently published coordinates for the classical triangulation network stations still be available to the public?
NGS has no intention of "abandoning" the classical triangulation network stations. These stations will still be published as part of the National Spatial Reference System; they just will not participate in The Readjustment of the NSRS. When you look at the level of distortion that is anticipated to be removed by this adjustment, it's on the order of 3-7 cm. That's in the noise of the positional uncertainty of the classical network, which in most cases is good to 10-40 cm. The transformation algorithm will allow us to model the positions of the classical network to fit more closely with the GPS data.

What happens afterwards?
First, a report on the project will be written in October 2007 through December 2007. Then work will proceed on building datum transformation grids (horizontal and vertical) between the newer and older coordinates. Plans will be developed and executed for adjustment of Hawaiian and Alaskan GPS networks. We continue reference frame maintenance work for both NAD 83 and ITRF coordinate sets. And, of course, we will be training our users on the network and local accuracies.

Why not abandon NAD 83 and use ITRF instead?
The legislation of many states specifies NAD 83. A burden would be imposed on the states if they were requested to change their laws. Instead, final coordinates will be published in both the NAD 83 and ITRF reference frames. By maintaining both reference frames, the greatest number of users will be served.

What are local and network accuracies?
A local accuracy of a control point is a value that represents the uncertainty of its coordinates relative to other directly connected, adjacent points at the 95-percent confidence level. It will be an approximate average of the individual local accuracy values between this control point and other observed control points used to establish its coordinates. A network accuracy of a control point is a value that represents the uncertainty of its coordinates with respect to the geodetic datum at the 95-percent confidence level. The datum is considered to be best expressed by the Continuously Operating Reference Stations (CORS). A more detailed explanation can be found in the following FGCD document:

http://www.fgdc.gov/standards/documents/standards/accuracy/

What coordinate system (NAD 83 (NSRS), or ITRF, or both) will the adjustment actually be done in?
The adjustment will be performed in NAD 83 (NSRS) and the final coordinates will be transformed to ITRF. Just prior to the Readjustment of the NSRS a transformation of the latest ITRF (200x) Continuously Operating Reference Stations (CORS) coordinates to NAD 83 (NSRS) will be made. Coordinates for CORS stations that have participated in the GPS reductions of any GPS survey included in the Readjustment of the NSRS will be constrained.

What will the NAD 83 coordinates from the Readjustment of the NSRS be called?
NAD 83 coordinates from the Readjustment of the NSRS will be labeled NAD 83 (NSRS). Date tags, such as NAD 83 (19xx) will not be used.


Last updated by Maralyn.Vorhauer on June 7, 2004