FREQUENTLY ASKED QUESTIONS
When will the new adjustment be finished?
The modified master plan has initiation of the Helmert Block retrievals in
June 2005 with completion on February 10, 2007.
Could it be completed sooner?
Yes, if all software is completed and tested for beginning the block retrievals
in June 2005, it is possible that the new coordinates could be computed and
available in 12-15 months.
When will I see new coordinates in my area?
Because Helmert Blocking is essentially a method of doing a simultaneous
adjustment of all data, all coordinates will be available upon completion of
the project-scheduled to be no later than February 10, 2007.
When will I know if the contingency adjustment is executed for my area?
There are currently no plans for contingency adjustments; however, if the
option becomes necessary because of delays in the implementation of Helmert
Blocking software, the National Readjustment Web Page will have an
announcement and a link showing the contingency schedule.
When will I see the new network and local accuracies?
These fields will be populated in the data sheets at the same time as the new
coordinates appear. However, should the contingency option be necessary, these
adjustments will not provide the new accuracy values.
What is the deadline for submission of a GPS UDN project for the
readjustment?
The deadline for submission of a GPS UDN project will be June 1, 2005. Projects
received by that date and ready for database loading will participate in the
new adjustment. Projects received after that date or which cannot be
immediately loaded in the database, will not participate in the adjustment.
These projects will be loaded and published and then readjusted upon completion
of the National Readjustment itself.
What about classical horizontal control surveys?
The Readjustment of the NSRS will contain only GPS projects. At the completion
of the project, datum transformation grids will be developed to support
those legacy data.
Will the currently published coordinates for the classical triangulation
network stations still be available to the public?
NGS has no intention of "abandoning" the classical triangulation network
stations. These stations will still be published as part of the National
Spatial Reference System; they just will not participate in The Readjustment
of the NSRS. When you look at the level of distortion that is anticipated to
be removed by this adjustment, it's on the order of 3-7 cm. That's in the
noise of the positional uncertainty of the classical network, which in most
cases is good to 10-40 cm. The transformation algorithm will allow us to
model the positions of the classical network to fit more closely with the GPS
data.
What happens afterwards?
First, a report on the project will be written - probably in the 3 months
following the completion of the adjustment. Then work will proceed on building
datum transformation grids between the newer and older coordinates. Plans will
be developed and executed for adjustment of the Hawaiian, Alaskan, and Pacific
Island GPS networks. We continue reference frame maintenance work for both
NAD83 and ITRF coordinate sets. And, of course, we will be training our users
on the use of network and local accuracies.
Why not abandon NAD 83 and use ITRF instead?
The legislation of many states specifies NAD 83. A burden would be
imposed on the states if they were requested to change their laws.
Instead, final coordinates will be published in both the NAD 83 and ITRF
reference frames. By maintaining both reference frames, the greatest
number of users will be served.
What are local and network accuracies?
A local accuracy of a control point is a value that represents the uncertainty
of its coordinates relative to other directly connected, adjacent points at the
95-percent confidence level. It will be an approximate average of the
individual local accuracy values between this control point and other observed
control points used to establish its coordinates. A network accuracy of a
control point is a value that represents the uncertainty of its coordinates
with respect to the geodetic datum at the 95-percent confidence level. The
datum is considered to be best expressed by the Continuously Operating
Reference Stations (CORS). A more detailed explanation can be found in the
following FGCD document: